Mumbai Builder Delivery Report – November 2026

Has the builder kept the completion date it promised the regulator? PropX8 checked 401 projects by 279 builders on the MahaRERA website. Only 320 (80%) have kept the original completion date; 81 (20%) have moved it, by about 27 months on average. Extensions MahaRERA gave all projects (COVID-19 and the automatic four-month extension of 2026) are not counted.

Projects checked on MahaRERA
401
Kept the original completion date
80%
Moved the completion date
20%
Average move (dates that moved)
2 years 3 months

Builder-wise record on MahaRERA

Builders with at least 2 projects checked, most checked first. PropX8 does not rate builders; this is the record as MahaRERA shows it.

BuilderCheckedKept dateMoved dateLongest moveCompletedComplaintsWith litigation
DGS Group770–01 (1 pending)1
Gurukrupa Realcon6511 year212
H Rishabraj Group660–101
Kalpataru Group6422 years 6 months3175 (13 pending)4
Lodha Group6331 year 8 months29 (2 pending)2
Nicco Group6516 months100
Samarpan Homes and Developers660–023
Chandak Group550–036 (3 pending)3
Ruparel Realty5234 years 2 months0159 (6 pending)1
Shreeji Sharan Group550–01 (1 pending)1
Arkade Group440–103
Pranav Constructions440–001
Romell Group4221 year 5 months110
Sanghvi Realty440–000
Shreeji Construction4313 years 6 months116 (1 pending)1
Ajmera Group3123 years 2 months010
Alliance City Developers330–000
Avyukta Realty330–000
Dotom Realty330–010
Dynamix Group3032 years 8 months121 (4 pending)2
Godrej Properties330–05 (1 pending)1
Kolte Patil330–11 (1 pending)1
Mahindra Lifespace330–02 (2 pending)1
Multi Space Developers330–000
Oberoi Realty330–112 (2 pending)1
Platinum Corp330–1133
Satellite Group3212 years015 (6 pending)1
Shree Mahavir Group330–100
Adani Realty2112 years185 (16 pending)2
Advent Developers2112 years000
Agarwal Group of Companies2111 year03 (2 pending)0
Avant Group220–001
Bharat Realty220–001
Bhoomi Group2112 years100
Dream India Group220–000
Fortune Group220–02 (1 pending)0
Goyal Realty2113 months000
Hubtown220–18 (3 pending)1
K Raheja Corp2111 year112
Kabra Group220–11 (1 pending)0
Khandelwal Group220–000
L&T Realty220–002
Lashkaria Group2111 year100
Lotus Developers2114 years 2 months031
Meghna Realty220–100
Mesacon Group220–100
Metro Realty220–000
Modirealty220–000
Panchnaad Group21111 months011
Pride Group2111 year021
Raymond Realty220–011
Royal Realtors220–000
Rustomjee220–12 (2 pending)0
Sajay220–011
Sapphire Developers220–000
Sejal Realty220–001
Shelaji Group220–000
Sheth Creators220–015 (8 pending)2
Shraddha Prime Projects220–010
Smgk group220–002
Sunteck Realty2026 years 5 months076 (7 pending)1

"Kept date": the current MahaRERA completion date is the one first registered. "Completed": shown as completed on MahaRERA for every wing. "With litigation": projects for which MahaRERA lists litigation. A complaint is not by itself a finding against the builder.

Questions

How many Mumbai housing projects keep their MahaRERA completion date?

Of the 401 projects PropX8 checked on MahaRERA (as of November 2026), 320 (80%) have kept the completion date first registered with MahaRERA and 81 (20%) have moved it. Extensions MahaRERA gave all projects, COVID-19 and the automatic four-month extension of 2026, are not counted as delays.

By how much do completion dates move?

Among the projects whose date moved, the move averages about 27 months beyond the original MahaRERA completion date, not counting the extensions MahaRERA gave all projects.

Where does this data come from?

From each project's public registration page on the MahaRERA website (Maharashtra Real Estate Regulatory Authority), checked by PropX8 staff: the original and current completion dates, extensions, status, occupancy certificate, litigation and complaints. A complaint is not by itself a finding against the builder.

Method: PropX8 staff read each project's registration page on the MahaRERA website (maharera.maharashtra.gov.in) and record the dates, status, occupancy certificate, litigation and complaints. Last check: 6 November 2026. Dates can change after our check; confirm on MahaRERA before booking. You may quote these figures with a link to this page.